AI- 50027
Commissioners Court
Meeting Date: 04/05/2021  
Amendment #1 with BGE, Inc.
Submitted By: Tracy Homfeld
Department: Engineering  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
 
The FM 546 Corridor Analysis study began in 2020 with the goal of realigning and widening the existing FM 546 from Princeton to McKinney in order to provide another east-west route for travelers who are presently using the overloaded US 380.
 
BGE was awarded the Phase 1 contract in April of 2020 which included the section from Bridgefarmer Rd, in Lowry Crossing to US 380 in Princeton. We were able to expedite this Phase since this section of roadway would not be on the TxDOT roadway system and had various sections that had already been developed in the city of Princeton. The final public meeting for the selection of an alignment was held on March 25, 2021.
 
We are ready to start phase 2 which will determine, and environmentally clear, a feasible alignment for a 6-lane major thoroughfare from Bridgefarmer Rd. in Lowry Crossing to the intersection of Harry McKillop Blvd and the current FM 546 in McKinney, TX. This Phase of the analysis will require extensive coordination with TxDOT and many other stakeholders in the area and will include the following tasks: alignment analysis, public/stakeholder involvement, schematic design, NEPA/EA, minor level of service (LOS) traffic analysis, geotechnical investigations, SUE, field surveying, and ROW mapping.
 
We anticipate this effort to take approximately a year and a half. Final design is not included in this contract and would come later once construction funding is identified.
 
The total cost for this project is $2,188,240.69. Funds are available in the RI18005CO, FM 546/CR400 Project account. The breakdown of the cost is in the attached Exhibit “C” Fee Schedule. Staff has negotiated the scope and fee and is recommending approval.
ACTION:
We request consideration of the approval of the Contract Amendment #1 with BGE, Inc. to include Phase 2 engineering services for FM 546 from Bridgefarmer Rd in Lowry Crossing, TX to south of the McKinney Airport at Harry McKillop Blvd.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of amendment No. 1 to the contract with BGE, Inc., Agr. 2019-210, Professional Services, Engineering, Alignment Study, Environmental Analysis, and Preparation of Design Schematic for FM 546 from Bridgefarmer Rd to CR 400, to add phase II services for FM 546 from Bridgefarmer Rd in Lowry Crossing, TX to South of McKinney Airport at Harry McKillop Blvd for corridor alignment analysis, public/stakeholder involvement, schematic design, NEPA/environmental analysis, traffic analysis, geotechnical investigation, subsurface utility engineering, field surveying, and ROW mapping for the amount of $2,188,240.69. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $2,188,240.69 for Amendment No. 1 to the contract Agr. 2019-210, Professional Services, Engineering, Alignment Study, Environmental Analysis and Preparation of Design Schematic for FM 546 from Bridgefarmer Rd to CR 400 with BGE, Inc. Amendment adds Phase II services for FM 546 from Bridgefarmer Rd in Lowry Crossing to south of the McKinney Airport at Harry McKillop Blvd. 2018 Bond Fund (4022).
Auditor's Office Action
Bond Funds available.
Commissioners Court
No. 1 to Professional Services, FM 546 Alignment Study, Environmental Analysis and Preparation of Design Schematic (Contract No. 2019-210) with BGE, Inc. to add Phase 2 engineering services for FM 546 from Bridgefarmer Rd in Lowry Crossing, TX to south of the McKinney Airport at Harry McKillop Blvd, and further authorize the Purchasing Agent to finalize and execute same, Engineering. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $2,188,240.69
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18005CO-4022-750300013-809250
Fund Transfers
Attachments
Court Order 2021-271-04-05
Memo
Amendment No. 1
Scope Phase II
Fee Proposal Phase II
Phase II Study Limits Map
Form 1295
2252 Certification