Print Back to Calendar Return
AI- 48467
Commissioners Court
Meeting Date: 07/13/2020  
FYI - Change Order No. 1 - Justice Center, Upgrade Pneumatic to Electronic Actuators - ABM Building Services, LLC
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 1 to ABM Building Services, LLC for IFB 2018-162, Construction, Upgrade Pneumatic to Electronic Actuators.
PCO 3- Owner requested credit to remove the installation of 16 DOC actuators from the scope of work. These 16, out of 315 actuators bid, could not be located by county staff, so they could be replaced by the contractor. It was determined that the actuators were not installed in original construction. The 16 actuators and panels were taken in to stock by the county so the credit is for labor only. ($14,250.26)
Total for this Change Order - ($14,250.26) or 1.93% of contract
Total Change Orders for the Project - ($14,250.26) or 1.93% of contract
This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to ABM Building Services, LLC for Construction, Collin County Justice Center, Upgrade Pneumatic to Electronic Actuators, IFB 2018-162 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 1 for IFB 2018-162, Construction, Upgrade Pneumatic to Electronic Actuators with ABM Building Services in the amount of ($14,250.26) to remove the labor cost of installing 16 DDC actuators from the project scope that were not needed.  New contract total is $725,681.74. Permanent Improvement Fund (0499).
Auditor's Office Action
Funds available in the Permanent Improvement Fund.
Commissioners Court
Change Order No. 1 to Construction, Upgrade Pneumatic to Electronic Actuators (IFB No. 2018-162) with ABM Building Services, LLC to provide various changes to the contract, Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: -14,250.26
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: PAN41002-0499-400108002-809101
Fund Transfers
Remarks:
CREDIT TO PROJECT PAN41002.
Attachments
Memo and PCO3
Change Order 1

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved