Change Order No. 1 to Sedalco Construction Services for Construction,Phase 2, Central Plant
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners Court for Change Order No. 1 to Sedalco Construction Services for IFB 2022-299, Construction: Collin County Adult Detention Facility, Phase 2 Addition, Central Utility Plant (CUP).
PCO 3 – Engineer required pier and foundation changes. During the shop drawing phase the modular plant manufacturer required changes in the piers and foundation to support the modular plant and cooling tower. $48,895.29
Total for this change order – $48,895.29 or 0.19% of contract
Total changes for this contract – $48,895.29 or 0.19% of contract
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 1 to Sedalco, Inc. for IFB 2022-299 Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. (ha)
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $48,895.29 for Change Order No. 1 to IFB 2022-299, Construction: Collin County Adult Detention Facility, Phase 2 Addition, Central Utility Plant with Sedalco, Inc. New contract total is $25,531,417.29. ARPA Funds (2132).
Auditor's Office Action
Funds available in the amount of $48,895.29 in the ARPA Fund (2132).
Commissioners Court
Change Order No. 1 to Construction: Collin County Adult Detention Facility, Phase 2 Addition, Central Utility Plant (IFB No. 2022-299) with Sedalco, Inc. to add engineer required pier and foundation changes to the contract, Construction & Projects.