Request Commissioners Court consideration and approval of Amendment No. 7 to Brinkley Sargent Wiginton Architects, Inc., Contract RFQ 2021-353.
Medical Mental Health Facilities:
City of McKinney required inspection of private storm and sanitary sewer lines - $7,070.
Central Utility Plant:
Survey and design to redirect the sanitary sewer line because of conflict with the chilled water lines. $6,500.
City of McKinney required inspection of private storm and sanitary sewer line - $3,030.
City Required topographic survey to thicken existing fire lane at courthouse employee parking lot - $5,500.
Total for this amendment - $22,100. or 0.030%
Total changes for this contract - $506,620. or 0.007%
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Contract Amendment No. 7 to RFQ 2021-353, Professional Services, Architectural, Adult Detention Center Expansion, Phase 2 & 3 with Brinkley Sargent Wiginton Architects, Inc. Further, authorize the Purchasing Agent to execute the contract amendment. (ha)
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $22,100 for Contract Amendment No. 7 to RFQ 2021-353, Professional Services, Architectural, Adult Detention Center Expansion, Phase 2 & 3 with Brinkley Sargent Wiginton Architects, Inc. New contract total is $7,932,476. ARPA Funds (2132).
Auditor's Office Action
Funds available in the amount of $22,100.00 in the ARPA Fund (2132).