FYI Change Order No. 2 to Criterion Contractors, Inc
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners' Court for Change Order No. 2 to Criterion Contractors, Inc for Construction, Modifications to Precinct 3 Constable and Justice of the Peace, 920 E. Park Blvd. (IFB No. 2021-129).
PCO 7 – City of Plano required add to comply with zoning standards. The City is requiring us to alter the bollard layout in the bid plans. This is causing the closing of three parking spaces, removal of wheel stops, the addition of concrete, and landscaping and sprinkler work. This will also extend the completion date by 30 days.
Total for this Change Order – $12,459.60 or 1.61% of contract
Total Change Orders for the Project – $21,691.90 or 2.80% of contract
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 2 to Criterion Contractors, Inc. for Construction, Modifications to Precinct 3 Constable & Justice of the Peace, 920 E. Park Blvd., IFB 2021-129 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $12,459.60 for Change Order No. 2 to IFB 2021-129, Construction, Modifications to Precinct 3 Constable and Justice of the Peace, 920 E. Park Blvd with Criterion Contractors, Inc. New contract total is $786,758.90. 2018 Tax Notes (4406).
Auditor's Office Action
Tax note funds available.
Commissioners Court
Change Order No. 2 to Construction, Modifications to Precinct 3 Constable & Justice of the Peace, 920 E. Park Blvd. with Criterion Contractors, Inc. to make various changes to the contract, Construction & Projects.