TThe Engineering Department requests approval of Change Order No. 1 to the construction contract with RPMx for the CCOL3C Project. Change Order No. 1 will allow for drill shaft cores to be performed per TxDOT Specifications, an electric gate and cattle guard, additional bridge deck steel and steel casing for a drill shaft at the East Fork Trinity River bridge. The change order will remove the monitoring well termination item since this work was done by others.
Change Order No. 1 results in a net contract increase of $229,071.64 revising the total construction contract amount to $62,312,797.94.
$88,335.78 is available in RI18OL002-4021-750300013-809280
$140,735.86 is available in RI18OL002-4030-750300013-809280
Recommended Action: It is requested that the Commissioners Court
-approve Change Order No. 1, increasing the CCOL3C contract by $229,071.64, for a total construction contract amount of $62,312,797.94.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of change order No. 1 to the contract with RPMx Construction, LLC, IFB 2023-303, Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75, to add drill shaft cores, an electric gate and cattle guard, additional slab reinforcement, a permanent 36" drill shaft casing, and to delete one gate and the capping and terminating of a monitoring well for the total amount of $229,071.64 and a new total contract amount of $62,312,797.94. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $229,071.64 for Change Order No. 1 to IFB 2023-303, Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75 with RPMx Construction, LLC. New contract total is $62,312,797.94. 2018 Bond Fund (4021 & 4030).
Auditor's Office Action
2018 Bond funds available (4021 & 4030).
Commissioners Court
No. 1 to Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75 (IFB No. 2023-303) with RPMx Construction, LLC to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Engineering.