Change Order No. 3 to Sedalco, Inc. for Construction: CCADF Medical Mental Health Expansion
Submitted For:
Sandeep Kathuria
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
CONSENT
Agenda Area:
Change Order
Information
Department Action
Request Commissioners Court consideration and approval of Change Order No. 3 to Sedalco, Inc. for Contract No. 2023-398, Construction: CCADF Medical Mental Health Expansion.
PCO 001 -City of McKinney required changes to Civil plans. Changes were issued to the Contractor by the Architect through PR#0l. These changes include relocation of the fire riser room, sizing and quantity changes of utility piping, quantity of sidewalk & paving changes, and changes in elevations of earthwork. These changes extend the critical path of the project by 22 days, therefore the Contractor's additional general conditions are included in this change order.
This change order adds 22 calendar days to the schedule's critical path.
Total amount of this change order is- $309.452.78 or 0.29% of contract.
Total Change Orders for this Project - $599.706.77 or 0.57% of contract.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Change Order No. 3 to Sedalco, Inc. for CSP 2023-398, CCADF Medical Mental Health Expansion, per the attached documents. Further, authorize the Purchasing Agent to execute the change order. (ha)
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $309,452.78 for Change Order No. 3 to 2023-398, Construction, CCADF Medial Mental Health Expansion with Sedalco, Inc. New contract total is $106,032,306.77. ARPA Fund (2132).
Auditor's Office Action
Funds available in the amount of $309,452.78 in the ARPA Fund (2132).
Commissioners Court
No. 3 to CCADF Medical Mental Health Expansion (CSP No. 2023-398) with Sedalco, Inc. make various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects.