FYI to Commissioners' Court for Change Order No. 3 to JJ Red Commercial Roofing, LLC, IFB No. 2017-320, Construction, Collin County Adventure Camp Roof Replacements. This change order is to remove replacement of decking on South Pavilion, with the exception of two (2) decking boards replaced, from the scope of work per JJ Red Commercial Roofing Change Order Request dated 6/18/18.
Total deduction - $1,749.00
This change totals - $1,749.00 decrease
Total change orders for the project - $3,749.00 decrease or -0.016%
Purchasing Department Action
FYI notification to Commissioners' Court for Contract Change Order No. 3 to JJ Red Commercial Roofing, LLC, IFB No. 2017-320, Construction, Collin County Adventure Camp Roof Replacements. This change order is to remove replacement of decking on South Pavilion, with the exception of two (2) decking boards replaced, from the scope of work per JJ Red Commercial Roofing Change Order Request dated 6/18/18. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 3 to IFB 2017-320, Contruction, Collin County Adventure Camp Roof Replacements with JJ Red Commercial Roofing, LLC to remove replacement decking on South Pavilion with the exception of two decking boards replaced. Change Order reduces the contract by $1,749 bringing the new contract total to $236,891.
Auditor's Office Action
Funds available in the County Insurance Fund.
Commissioners Court
Change Order No. 3 to Construction, Collin County Adventure Camp Roof Replacements (IFB No. 2017-320) with JJ Red Commercial Roofing, LLC to remove replacement of decking on South Pavilion, with the exception of two (2) decking boards replaced, from the scope of work, Construction & Projects.