FYI - Change Order No. 1 - Renovations to Beverage Bars in Detention Center Cluster Four
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners' Court for Change Order No. 1 to First Choice Restaurant Equipment & Supply for the Renovations to the Beverage Bars in Detention Center Cluster Four.
Owner requested change order to move a drain to install a sink. This change involves removing part of a block wall, moving the drain, replacing block, and then painting.
Total for this Change Order - $1,350.00 or 4.6% of contract.
Total Change Orders for the Project - $1,350.00 or 4.6% of contract.
The change order was approved by County Administrator per Court Order 2007-180-02-27.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to 1st Choice Restaurant Equipment & Supply, LLC, IFB 2019-140, Renovations to Beverage Bars in Detention Center Cluster Four per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $1,350 for Change Order No. 1 to IFB 2019-140 with 1st Choice Restaurant Equipment & Supply, LLC for renovations to the beverage bars in the Detention Center. Permanent Improvement Fund (0499).
Auditor's Office Action
Funds available in the Permanent Improvement Fund.
Commissioners Court
Change Order No. 1 to Renovations to Beverage Bars in Detention Center Cluster Four (IFB No. 2019-140) with 1st Choice Restaurant Equipment & Supply LLC for owner requested change to move a drain to install a sink, Construction Projects.