P25 radio system change order #11 which includes
Generator Inspection at our Princeton and Farmersville Towers - $2,919.90
Generator Inspections- PM Time - $1,138.88
Replacement parts and labor for damaged equipment from a water leak in the Verona shelter -$2,876.70
SUA System Upgrade 2020 - $12,000 (Necessary because of the project delays)
The total cost of this change order is $18,935.48. The new contract value to $11,477,369.97, making the contract delta $769,588.97.
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval of Amendment No. 11 to Contract 2016-020, P25 Trunked Radio System Replacement in the amount of $18,935.48 making the new contract amount $11,477,369.97 and authorize Purchasing Agent to execute same. sh
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $18,935.48 for Amendment No. 11 to Contract 2016-020, P25 Trunked Radio System Replacement. New contract total is $11,477,369.97.General Fund (0001).
Auditor's Office Action
Funds available in the General Fund.
Commissioners Court
No. 11 to P25 Trunked Radio Replacement (Contract No. 2016-020) with Motorola Solutions, Inc. to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Sheriff.