Public Works requests Commissioners Court consideration to renew IFB 2020-241 CTB & Cement Stabilized Backfill with Martin Marietta Materials, Inc.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of contract renewal for IFB No. 2020-241, Cement Treated Base & Cement Stabilized Backfill with Martin Marietta Materials, Inc. to renew contract for the period of October 1, 2021 through September 30, 2022. gz
Renewal 1 of 3; FY21 YTD $84,227.50
HR and/or IT Action
Budget Department Action
Budgeted funds available upon adoption of the FY 2022 Budget for the renewal of IFB 2020-241 Road Materials: Cement Treated Base & Cement Stabilized Backfill with Martin Marietta, Inc. Contract extension for one (1) year to include same terms, conditions and pricing set forth in the original award to include any previously executed amendments/change orders. Contract period October 1, 2021 through September 30, 2022. (1010)-Road and Bridge Fund.
Auditor's Office Action
Funds available in the Road and Bridge Fund.
Commissioners Court
Cement Treated Base & Cement Stabilized Backfill (IFB No. 2020-241) with Martin Marietta Materials, Inc. to extend the contract for one (1) year through and including September 30, 2022, Public Works.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
$9,524,000
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
1010-75001-0001-68-30-0000-637529-
2:
1010-75001-0001-68-30-0000-637532-
Fund Transfers
Remarks:
Budgeted funds available upon adoption of the FY 2022 Budget.