The Texas Department of Transportation has developed plans to make improvements to the bridge located at FM 547 and Sabine Creek. As is always TxDOT’s policy, they are requiring Collin County provide 10% of the cost of the ROW and utility relocations. For this project that amounts to $7,429.40
Action Requested: It is requested that the Commissioners Court
1) Approve the attached agreement with the Texas Department of Transportation,
2) Authorize the County Judge to execute the agreement,
3) Authorize a budget adjustment to transfer $7,430 from project RI18016 to a new project set up by the Auditor, and;
4) Authorize payment of this amount when the agreement is fully executed and the funds have been
transferred into the appropriate new account.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of an Agreement to Contribute Right of Way Funds (FIXED PRICE) for certain highway improvements on FM 547 at Sabine Creek. Further, authorize the County Judge to execute same. MD
Collin County's participation is NTE $7,429.40.
HR and/or IT Action
Budget Department Action
Funds available in the amount of $7,429.40 for the Agreement to Contribute Right of Way with TxDOT for improvements to the bridge at FM 547 at Sabine Creek (RI18021). Collin County's participation is not to exceed $7,429.40. Budget Adjustment totaling $7,430 is included. 2018 Bond Fund (4022).
Auditor's Office Action
Bond Funds available.
Commissioners Court
Agreement to contribute right of way funds (fixed price) with TxDOT for certain highway improvements on FM 547 at Sabine Creek, Engineering.