Public Works requests Commissioners Court approval to renew 2020-241, CTB & Cement Stabilized Backfill with Martin Marietta Materials, Inc.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of change order No. 1 to IFB 2020-241, Road Materials, Cement Treated Base & Cement Stabilized Backfill with Martin Marietta Materials, Inc. to 1) Remove Line 1 from the contract; 2) include a price redetermination per section 4.6 of the contract per the attached documentation; and 3) to extend the contract for the period October 1, 2022 continuing through and including September 30, 2023; and 4) allow Purchasing Agent to execute the same. gz
Renewal 2 of 3; FY21 $79,195.43 FY22 YTD $20,063.71
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No.1 to the renewal of IFB 2020-241 Road Materials: Cement Treated Base & Cement Stabilized Backfill with Martin Marietta, Inc. Change order to renew contract for one (1) year and make various changes to the contract. Contract period October 1, 2022 through September 30, 2023. (1010)-Road and Bridge Fund.
Auditor's Office Action
Funds available in the Road and Bridge Fund.
Commissioners Court
No. 1 to Road Materials: Cement Treated Base & Cement Stabilized Backfill (IFB No. 2020-241) with Martin Marietta Materials, Inc. to extend the contract for one (1) year through and including September 30, 2023, make various changes, and further authorize the Purchasing Agent to finalize and execute same, Public Works.