FYI to Commissioners’ Court for Change Order No. 2 to Acumen Enterprises Inc., for IFB 2022-198, Repairs to Second Floor Walkway and First Floor Soffit, 900 E. Park Blvd., Plano, TX.
Contractor requested to add twenty-three calendar days to completion date for weather delays. Previous completion date: 1/14/23. New completion date: 2/7/23.
Total for this change order - $0.00.
Total changes for this contract - $13,514.00 or 1.80% of contract.
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 2 to Acumen Enterprises, Inc. for IFB
2022-198, Construction, Exterior Repairs to Second Floor Walkway & First Floor Soffit, 900E. Park Blvd., Plano
per the attached documents. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 2 to IFB 2022-198, Repairs to Second Floor Walkway and First Floor Soffit, 900 E. Park Blvd., Plano, TX with Acumen Enterprises Inc. to extend the contract completion date to February 7, 2023. No action by Budget.
Auditor's Office Action
No action by Auditor.
Commissioners Court
Change Order No. 2 to Construction, Exterior Repairs to Second Floor Walkway & First Floor Soffit, 900 E. Park Blvd., Plano to add twenty-three (23) calendar days to completion date for weather delays, Construction & Projects.