Change Order No.10 to Ratcliff Construction for Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners Court for contract change order No. 10 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County
Adult Detention Facility, Phase 1. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
PCO 29 - Architect requested add to install ramps. The provided elevations for floor connections to the existing building were not correct causing the installation of ramps in the new building. The Architect is reimbursing us for this change. $30,071.10
Total for this change order - $30,071.10 or 0.07% of contract
Total changes for this contract - ($127,254.86) or 0.33% of contract
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 10 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No. 10 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition with Ratcliff Constructors, L.P. totaling $30,071.10. New contract total is $38,132,745.14. 2007 Bond Fund (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 10 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to provide various changes to the contract, Construction & Projects.