FYI to Commissioners Court for Change Order No. 4 to Acumen Enterprises Inc., for IFB 2022-198, Repairs to Second Floor Walkway and First Floor Soffit, 900 E. Park Blvd., Plano, TX.
This change order was previously approved by the County Administrator per Court Order 2007-180-02-27.
PCO 4 - Credit to remove steel from work scope per unit price contract. ($5,288.88)
Total for this change order - ($5,288.88) or (0.7%) of contract
Total changes for this contract- $14,887.12 or 1.99% of contract
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 4 to Acumen Enterprises, Inc. for IFB 2022-198, Construction, Exterior Repairs to Second Floor Walkway & First Floor Soffit, 900E. Park Blvd., Plano per the attached documents. mlm
HR and/or IT Action
Budget Department Action
Notification of Change Order No. 4 to IFB 2022-198, Construction, Exterior Repairs to Second Floor Walkway & First Floor Soffit, 900E. Park Blvd., Plano in the amount of ($5,288.88) with Acumen Enterprises, Inc. New contract total is $763,887.12. Permanent Improvement Fund (0499).
Auditor's Office Action
No action required by Auditor.
Commissioners Court
Change Order No. 4 to Construction, Exterior Repairs to Second Floor Walkway & First Floor Soffit, 900 E. Park Blvd., Plano (IFB No. 2022-198) with Acumen Enterprises, Inc. for a credit issued by the vendor for steel labor, Construction & Projects.