Ratcliff Constructors for Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners Court for contract change order No. 17 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County Detention Facility, Phase 1.
PCO 62 - Architect required change to Sally Port drive opening height. The Architect will repay the County for this change. $22,348.71 Plus 2 days added to the schedule.
PCO 67 - Engineer required add to support one area of roof deck. Added one piece of angle. $1,523.55
New completion date, 5/22/24.
Total for this change order - $23,872.26 or 0.06% of contract
Total changes for this contract - $444,849.31 or 1.16% of contract
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 18 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. mlm
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $23,872.26 for Change Order No. 18 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition. New contract total is $38,704,849.31. 2007 Bond Fund (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 18 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to make various changes to the Contract, Construction & Projects.