Change Order to Sedalco, Inc. for CCADF Central Utility Plant
Submitted For:
Sandeep Kathuria
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
CONSENT
Agenda Area:
Change Order
Information
Department Action
Request Commissioners Court approval of a Change Order to Sedalco Inc. for IFB 2022-299, Construction, CCADF Phase 2 Addition, Central Utility Plant (CUP).
PCO #13 – Existing conditions require the installation of adapters to complete the chilled water tie-ins to the existing system. The fusion weld per the contract documents cannot be completed because existing valves will not completely close. The proposed adapters allow for the tie-in to be complete while the flow of water continues.
Total for this change order $58,456.70 or 0.023% of contract.
Total Change Orders for this Project - $2,775,107.40 or 0.11% of contract.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Change Order No. 6 to Sedalco, Inc. for IFB 2022-299 Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP per the attached documents. Further authorize the Purchasing Agent to execute the change order. (ha)
HR and/or IT Action
Budget Department Action
Funds available in the amount of $58,456.70 for Change Order No. 6 to IFB 2022-299 Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP with Sedalco, Inc. New contract total is $28,257,629.40. ARPA Funds.
Auditor's Office Action
Funds available in the amount of $58,456.70 in the ARPA Grant Fund (2132).
Commissioners Court
No. 6 to Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP (IFB No. 2022-299) with Sedalco, Inc. to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects.